The 508 km long Ahmedabad-Mumbai High Speed Bullet Train Corridor is rapidly taking shape. The only mountain tunnel on this route is built in Umargam. This single tunnel is 350 meters long, made up of the New Austrian tunneling method. This technique creates an internal layer of shotcrit, steel, mesh garder, wire mesh. Excavations are carried out after the rock bolt was mounted to stabilize the soil.
The work done so far in the project
More than 260 km of viaducts And the works of the 360 km pillar are completed.
Welding of rail on an RC track bed longer than 95 km and viaduct has begun.
The sound barrier was placed in Gujarat on viaducts more than 100 km long.
08 8 Structural work is completed on Gujarat 6 from bullet train stations.